Year 6 (FY 2003-2004), Waves 25 and 26 Funding Committed
Message Posted April 14, 2004

Congratulations to the following 7 Pennsylvania schools that
will be receiving Year 6, Waves 25 and 26 E-rate Funding Commitment

Letters.  With these waves, PA's schools and libraries will have been

committed more than $91 million in Year 6.

As a result of the FCC carrying over unspent funds from previous years (more
than $400 million), the SLD was able to provide internal connections funding

down to the 70% level.  Those funding commitments, along with others

at the priority 1 level, are included in this funding wave.  Internal

Connections funding will not be available for applicants at the 69% and

below discount

levels for Year 6.

Because these funding commitment decision letters are being issued after
March 1, applicants are automatically granted an additional year to purchase

these

items without seeking a service delivery extension from the SLD.  Therefore,

you have until September 30, 2005 to purchase/install internal connections

that are included in this wave.

A summary of the commitment is listed below, and detailed
information will be posted on the SLD web site under Funding

Commitments at: http://www.sl.universalservice.org/funding/.

If you find that your funding commitment letter does not arrive

in a timely manner, please call

the SLD ASAP to get a replacement (888-203-8100). All Year 6 correspondence

is being sent in YELLOW.

If you do not agree with your funding commitment decision letter, you have
60 calendar days to appeal from the date listed at the top of your FCDL.

Appeal instructions can be found at:

http://www.sl.universalservice.org/reference/AppealsProcedureYR4.asp.

Please let me know if you have questions concerning an appeal or would like

me to review it before it's submitted.

A few very important notes:

YOUR FCDL IS NOT THE LAST STEP.  YOU NOW MUST FILE THE FORM 486.

* The 486 tells the SLD 3 things:

1) that they are authorized to pay invoices (either BEAR or SPIFs)
2) which SLD-certified approver approved your technology plan

3) that you were CIPA compliant by start of services

This form must be filed within 120 of the service start date
or the date on the funding commitment letter, whichever is later.  If you

are receiving internal connections

funding, you may want to wait until after the product is delivered or

installed to complete the 486.

The 486 is available online or in paper format at:
www.sl.universalservice.org.

If you have any questions, please contact me at jtschell@comcast.net.

E-rate Year 6, Wave 25

Albert Gallatin Area SD                 $190,577.99
Aliquippa SD                    $116,518.67

Allegheny IU                    $196,358.04

Total, Wave 25                  $503,454.70

E-rate Year 6, Wave 26

Immaculate Heart School $36,368.36
Lower Moreland Twp SD           $9,600.00

Perkiomen Valley SD             $23,424.00

Tuscarora SD                    $31,488.76

Total, Wave 26                  $100,881.12

Julie Tritt Schell

jtschell@comcast.net
(717) 730.7133 (voice)
(717) 730.9060 (fax)