Category 2 Form 471 Filing Guide – FY 2021

February 1, 2021

Attached: Form 471 Category 2 Filing Guide – FY 2021

~ Bulk Upload Guide Coming Next ~

~ Be Sure to Read Helpful Hints Below ~

~ Register Now for Category 1, Form 471 Training: http://e-ratepa.org/?page_id=745 ~

Category 2 is the E-rate funding mechanism designed to fund networking equipment and infrastructure within a school or library building.  All eligible requests that have followed the proper bidding rules will be funded, regardless of E-rate discount, up to a building’s 5-year pre-discount cap (FY 2021 – FY 2025).  There are only 53 days left before the March 25, 2021 Form 471 Filing Window closes and the first funding wave is slated to be released in April.  So file early to be in one of the first waves!

CATEGORY 2 FILING GUIDE

Attached you will find the FY 2021 Category 2 Form 471 Filing Guide (enhanced for FY 2021), containing 90 slides, that provides step-by-step screenshots/instructions and hints/answers for three different types of funding requests as follows:

  • Wireless Equipment – 4 line items – WAPs/Licenses/Controller/Installation (starts on slide 20)
  • Network Switches – 2 line items (starts on slide 47)
  • Structured Cabling – 1 line item  (starts on slide 63)

Also, there is an additional section to assist applicants with submitting/certifying, printing the form, as well as slides to help with any revisions that must be made after the form has been submitted.  This section begins on slide 78.

WHAT’S NEW FOR FY 2021

There are 2 big improvements on the FY 2021 Category 2 Form 471, and a few small, but welcome, improvements, thanks to stakeholder input:

  • BIG!  No longer required to identify which buildings will receive equipment or associated per building costs
  • BIG!  Category 2 Budget Tool on the FRN Page works, showing up-to-date data
  • Easier navigation from FRN to FRN Line Items (this previously wasn’t intuitive because you had to click on the FRN Number on the Main FRN Page to get to the FRN Line Item Page).
  • Ability to easily access Narrative Text Box while creating FRN Line Items.  This is found at the bottom of the ‘Type of Connection’ Page.  No FRN Line Item Narrative Boxes are included.
  • Much better descriptions on how to create draft PDF when finishing form.

HELPFUL HINTS FOR FILING THE CATEGORY 2 FORM 471

1. Don’t Exceed Your Category 2 Budgets!

Because all Category 2 budgets have been reset for FY 2021 and because the budgets are now district-based instead of school-based, most applicants likely won’t exceed their C2 budgets for FY 2021.  Regardless, be certain to doublecheck that you’re not requesting more Category 2 funding for your district than what remains in your budget.  Why?  Your application will likely be moved to the end of the PIA review list, and PIA will just make you reduce your funding request anyway.  And while this sounds easy to do, it’s not because you will have to explain exactly which component from which FRN Line Item must be removed in order to come in under budget.  If a district’s C2 equipment costs exceed the available C2 budget, you have two choices:  1) list the amount that is “over budget” as ineligible on the FRN and then explain this in the narrative, or 2) remove components or reduce the cost of the components from an FRN entirely to come in under budget.  To see your available FY 2021 budget, go to:  https://opendata.usac.org/E-rate/E-rate-C2-Budget-Tool-FY2021-/8z69-hkn7 and enter your BEN on the right toolbox.

2. Multi-Year Product Licenses Eligibility

Product licenses are E-rate eligible and should be requested as Internal Connections on the 471.  The full cost of a multi-year license may be requested upfront in the year it will be purchased.  Under Type of Equipment, select “License” instead of Wireless Data Distribution (or other equipment type).

3. Basic Maintenance Services Are Not Considered Licenses

Be careful not to mistaken maintenance services as product licenses.  Also, E-rate rules do not permit the requesting of multi-year maintenance services in a single year – these must be amortized and requested in the funding year for which the service covers.

4. Have Structured Cabling Contracts be Single Priced

For structured cabling, try to have your vendor contracts be for a single price, by building – not broken down by widget.  Then just create 1 FRN Line Item in the Form 471.  Vendor invoices, therefore, also should have just a single price – not broken down by widget/connectors.

5. Break Out All Components into Separate FRN Line Items – Including Switches

If your Category 2 request contains multiple components, you must create a separate FRN Line Item for each component (model), and then show the # of units, and the cost per unit.  For example, a common mistake applicants make is to request just a single FRN Line Item for switches, with a single SKU.  Then during USAC invoicing, the invoices are denied because the individual components were not listed/approved on the Form 471.

6. Break Out Ineligible Costs

Firewalls:  Only the actual appliance and basic operating software are eligible.  Anti-virus, anti-spam, filtering, and DDOS features/software are not eligible and must be removed or cost-allocated.  If it’s a bundled package, your vendor can provide you with the accurate eligibility percentage.
UPSs:  Network Cards are not eligible and must be removed from your funding request.  Also, don’t forget that only eligible equipment may be connected to the UPSs.

7. Category 2 Contract Requirement

All Category 2 purchases require a signed contract prior to submitting the Form 471.  This can be as simple as signing/dating the vendor contract and including the contract term and any funding contingencies.  Before starting your Form 471, upload the signed contract into EPC.  Landing Page > Name of District > Contracts > Manage Contracts.  The Contract Module Guide can be found at: http://e-ratepa.org/?p=32998.   The PEPPM Contract Module Guide can be found at: http://e-ratepa.org/?p=32980.

8. Wisely Allocate C2 Budgets for Equipment Shared by a NIF

If a piece of Category 2 equipment is shared by a NIF, a portion of the cost of the equipment must be listed as “ineligible” to account for the NIF usage (core switches and wireless controllers are good examples of equipment that is often shared by NIFs).  Deciding which cost allocation method to choose — and making sure you do so correctly on your Form 471 — is important.  You can either 1) allocate the costs equally by # of buildings, or 2) allocate the costs on a weighted basis.   The second option requires some simple off-line math, but it is usually much more advantageous to use this method.  One such method for a wireless controller formula could be:  # of district WAPs in all buildings divided by # of WAPs in NIF.  For a core switch, it could be based on # of users or square footage.

9. Service Start Date Must Be 7/1/2021

The Service Start Date must always be July 1, not April 1.  Equipment is allowed to be purchased on or after April 1, and vendor invoices also may be dated on or after April 1.  But on the Form 471, where it asks for the Service Start Date, leave it populated to be 7/1/2021.  Note:  The Service Start Date is not the same as the Contract Award Date; the Contract Award Date is what you provide in the Contract Record as the date you signed the contract.

If you have any questions as you’re working through your Form 471, please don’t hesitate to e-mail me at jtschell@comcast.net.

Happy 471 Filing!

– Julie

Julie Tritt Schell

Pennsylvania E-rate Coordinator
717-730-7133 – o
jtschell@comcast.net
www.e-ratepa.org

You are HERE in the E-rate process:

eratecycle2-01

Site graciously hosted by the Capital Area IU 15 | Site designed and maintained by Silver Penny Studio